Industrial Implementation Company „WILPO“ Ltd.

+48 (32) 251-92-25 +48 (32) 257-08-68 +48 (32) 257-08-69

 

The official acceptance of four systems WILPO C 532hc in Kozienice Power Plant – 21 December 2017

January 4, 2018

The acceptance protocol of four WILPO C 532hc systems being a part of a new investment in Kozienice Power Plant (belonging to the Enea Group), was signed on 21.12.2017. The implemented devices are the part of the stoking system of a newly built power block of 1075 MW which was put into operation on 19.12.2017.

The fully calibrated measurement systems provide on-line monitoring of the quality parameters of coal delivered to the new power block by the two transport galleries.